AgPlus Additional Conditions for Purchase of Services

1. Performance

  1. The Contractor shall perform the Services in accordance with the Contract to the satisfaction of AGPLUS or its authorised representative. AGPLUS shall have the power to inspect and examine the performance of the Services at any reasonable time, provided that AGPLUS shall have given the Contractor reasonable notice of such inspection and examination. The Contractor shall provide all such facilities as AGPLUS may reasonably require for such inspection and examination.
  2. If AGPLUS finds that any part of the performance of the Services is inadequate or in any way differing from the Contract, other than as a result of default or negligence on the part of AGPLUS, the Contractor shall, at the Contractor’s own expense, re-schedule and perform the Services correctly within such reasonable time as may be specified by AGPLUS.
  3. AGPLUS may suspend the performance of the Services or any part thereof by written notice to the Contractor at any time. If the performance of the Services or any part thereof is suspended by AGPLUS for any reason other than default or negligence on the part of the Contractor, or if the performance of the Services or any part thereof is delayed by any act of AGPLUS, AGPLUS shall pay the Contractor for any loss incurred by the Contractor as a direct result of such suspension or delay, provided always that the total of the payments made to the Contractor under the Contract shall not exceed the Contract Price.
  4. The Contractor shall be allowed a reasonable extension of time for completion of the performance of the Services if the performance of the Services or any part thereof:
    1. is suspended by AGPLUS for any reason other than default or negligence on the part of the Contractor;
    2. is delayed by any act of AGPLUS; or
    3. is delayed by any industrial dispute or any other cause that the Contractor could not have prevented and for which the Contractor was not responsible.